Link milestone to activity PDF Print E-mail

ONLY for Project Managers.

Click on the tab Schedule and then on the Milestones view. To link the milestone to an activity, click on the name or the pencil icon in front of the milestone.

Link milestone to a project activity


1 Click on the drop-down list and select the activity to link the milestone with. "None" means that the milestone appears on the "root" activity of the project.