Edit project timesheet PDF Print E-mail

ONLY for project managers

Select a project, click on the Schedule tab and choose the "Timesheet" view.

Edit project timesheet with the project management tool Planzone

1 You can modify the time spent values entered by the team members, in the cells at the intersection of a row (activity) and a column (day).

2 Click on the "Integrate" button to integrate all time spent for the entire week. If you want to integrate only several days, use the green check marks at the bottom of each column.

The integration will update the "Time spent" column at the right and sum up all hours until the integration date. Simultaneously the "Remaining hours" column will be re-computed as the "allocated hours" minus the "time spent" (until the integration date).

3 You can "Lock" the timesheet, so that no team member can modify his/her timesheet any longer. Certainly you can "Un-lock" the timesheets if you change your mind.